Сукупність будівельних матеріалів, які було отримано в результаті ліквідації основного засобу та обладнання котельні за адресою: м. Мелітополь, вул. Дружби, 187/1
Published
03.08.20
Payment is expected
till 25.09.20
The agreement is paid. The decree is expected
till 17.08.20
Period of fulfillment of the terms of sale (period of appeal)
till 28.09.23
The object privatization is completed.
The object privatization is completed.
Contract details
Contract amount | 13`333.20 uah (not including WAT) | |
Agreement number | б/н | |
Date of signing | 27.07.2020 | |
Type of announcement | Announcement of the auction for the sale of small-scale privatization objects |
Information about Supplier
Name of legal entity | Жарчинський Сергій Станіславович | |
USREOU code | 3074122739 | |
Legal address | 72311, Україна, Запорізька область, м. Мелітополь, вул. Дружби, буд. 167/7 |
Documents of contract / changes
Signed agreement
|
Договір купівлі-продажу.PDF | |
Decree on confirmation of privatization
|
Наказ |
Nomenclature of the contract
1) |
Сукупність будівельних матеріалів, які було отримано в результаті ліквідації основного засобу та обладнання котельні за адресою: м. Мелітополь, вул. Дружби, 187/1
: 42990000-2 - Машини спеціального призначення різні
unknown (not applicable)
|
1 лот |
PERIODS
The status of the fulfillment of the stipulated conditions at a specific time point | Completed | |
Period type | Waiting for payment | |
Date when the deadline for action within Maystone runs out | 25.09.2020 18:00 | |
Date when the relevant conditions were fulfilled | 28.07.2020 14:29 | |
Date of period editing | 28.09.2020 14:30 |
The status of the fulfillment of the stipulated conditions at a specific time point | Partly completed | |
Period type | Completion of privatization | |
Date when the deadline for action within Maystone runs out | 17.08.2020 18:00 | |
Date when the relevant conditions were fulfilled | 28.09.2020 16:26 | |
Date of period editing | 28.09.2020 16:28 |
The status of the fulfillment of the stipulated conditions at a specific time point | Completed | |
Period type | Fulfillment of terms of sale | |
Date when the deadline for action within Maystone runs out | 28.09.2023 16:26 | |
Date when the relevant conditions were fulfilled | 28.09.2020 16:34 | |
Date of period editing | 28.09.2020 16:34 |
Contract in CDB
ID | c4e4056b1c65457e907d9a89458505ea | |
ContractID | UA-PS-2020-06-22-000123-3-11 |