Будівля гаражів та складу загальною площею 148,1 кв.м. за адресою: м.Львів, вул.Княгині Ольги, 104
Published
02.09.20
Payment is expected
till 02.11.20
The agreement is paid. The decree is expected
till 28.09.20
Period of fulfillment of the terms of sale (period of appeal)
till 07.09.23
The object privatization is completed.
The object privatization is completed.
Contract details
Contract amount | 1`328`002.00 uah (WAT included) | |
Agreement number | 256 | |
Date of signing | 01.09.2020 | |
Type of announcement | Announcement of the auction for the sale of small-scale privatization objects |
Information about Supplier
Name of legal entity | ГО СК "ПІВДЕННИЙ" | |
USREOU code | 35444913 | |
Legal address | 79053, Україна, Львівська область, м.Львів, ВУЛИЦЯ МУЗИКИ, БУДИНОК 34, КВАРТИРА 115 |
Documents of contract / changes
Signed agreement
|
Договір_куп_пр_КнОльги104_скан.pptx | |
Decree on confirmation of privatization
|
Довідка_оплата_КнОльги104.pptx | |
Decree on confirmation of privatization
|
Наказ_заверш_приват_КнОльги104.pptx |
Nomenclature of the contract
1) |
Будівля гаражів та складу загальною площею 148,1 кв.м. за адресою: м.Львів, вул.Княгині Ольги, 104. Одноповерхова цегляна будівля. Технічний стан задовільний.
CAV-PS code: 04210000-3 - Промислова нерухомість
Legacy classificator code 018:2000: 125 - Будівлі промислові та склади
The object is registered 72042725 from 01.11.2016
|
148.1 метри квадратні |
PERIODS
The status of the fulfillment of the stipulated conditions at a specific time point | Completed | |
Period type | Waiting for payment | |
Date when the deadline for action within Maystone runs out | 02.11.2020 17:00 | |
Date when the relevant conditions were fulfilled | 07.09.2020 00:00 | |
Date of period editing | 14.09.2020 09:29 |
The status of the fulfillment of the stipulated conditions at a specific time point | Completed | |
Period type | Completion of privatization | |
Date when the deadline for action within Maystone runs out | 28.09.2020 18:00 | |
Date when the relevant conditions were fulfilled | 07.09.2020 00:00 | |
Date of period editing | 19.01.2021 12:52 |
The status of the fulfillment of the stipulated conditions at a specific time point | Completed | |
Period type | Fulfillment of terms of sale | |
Date when the deadline for action within Maystone runs out | 07.09.2023 00:00 | |
Date when the relevant conditions were fulfilled | 09.09.2020 00:00 | |
Date of period editing | 19.01.2021 12:52 |
Contract in CDB
ID | 61a81ebdf38f4834a16aa094964808c1 | |
ContractID | UA-PS-2020-07-19-000014-3-11 |