Об’єкт незавершеного будівництва – малоповерхова житлова забудова у м. Енергодар. БД-13/1 (1 черга), БД-13/2 (1 черга)
Published
16.10.20
Payment is expected
till 14.12.20
The agreement is paid. The decree is expected
till 16.11.20
Period of fulfillment of the terms of sale (period of appeal)
till 18.11.23
The object privatization is completed.
The object privatization is completed.
Contract details
Contract amount | 319`200.00 uah (not including WAT) | |
Agreement number | 12/1-19 | |
Date of signing | 15.10.2020 | |
Type of announcement | Announcement of the auction for the sale of small-scale privatization objects by method of step-by-step of lowering the starting price |
Information about Supplier
Name of legal entity | ТОВ "П'ЯТА СТРАЖА" | |
USREOU code | 30604618 | |
Legal address | 04053, Україна, Київська область, Київ, вул. Артема, буд. 10 |
Documents of contract / changes
Signed agreement
|
ДКП від 15.10.2020.pdf | |
Decree on confirmation of privatization
|
Наказ рез-ти продажу Енергодар,Таврійський 6.pdf | |
Decree on confirmation of privatization
|
SCAN_12_1-19.PDF |
Nomenclature of the contract
1) |
Малоповерхова житлова забудова у м. Енергодар. БД-13/1 (1 черга), незавершена будівництвом.
CAV-PS code: 04150000-4 - Садибний (індивідуальний) будинок малоповерхового житлового будівництва
Legacy classificator code 018:2000: 242 - Інші інженерні споруди, не класифіковані раніше
The object is registered 501573223125 from 17.12.2014
|
144.6 метри квадратні |
2) |
Малоповерхова житлова забудова у м. Енергодар. БД-13/2 (1 черга), незавершена будівництвом
CAV-PS code: 04150000-4 - Садибний (індивідуальний) будинок малоповерхового житлового будівництва
Legacy classificator code 018:2000: 242 - Інші інженерні споруди, не класифіковані раніше
The object is registered 501616323125 from 17.12.2014
|
142.5 метри квадратні |
PERIODS
The status of the fulfillment of the stipulated conditions at a specific time point | Completed | |
Period type | Waiting for payment | |
Date when the deadline for action within Maystone runs out | 14.12.2020 17:00 | |
Date when the relevant conditions were fulfilled | 26.10.2020 00:00 | |
Date of period editing | 18.11.2020 15:51 |
The status of the fulfillment of the stipulated conditions at a specific time point | Partly completed | |
Period type | Completion of privatization | |
Date when the deadline for action within Maystone runs out | 16.11.2020 18:00 | |
Date when the relevant conditions were fulfilled | 18.11.2020 00:00 | |
Date of period editing | 19.11.2020 15:26 |
The status of the fulfillment of the stipulated conditions at a specific time point | Completed | |
Period type | Fulfillment of terms of sale | |
Date when the deadline for action within Maystone runs out | 18.11.2023 00:00 | |
Date when the relevant conditions were fulfilled | 19.03.2021 12:00 | |
Date of period editing | 30.03.2021 15:06 |
Contract in CDB
ID | b57fa5cc934d417aa96927466e700854 | |
ContractID | UA-PS-2020-08-19-000115-3-31 |