Водно-спортивна база "Локомотив"
Published
02.07.21
Payment is expected
till 15.06.20
The agreement is paid. The decree is expected
till 17.08.21
Period of fulfillment of the terms of sale (period of appeal)
till 06.08.24
The object privatization is completed.
The object privatization is completed.
Contract details
Contract amount | 11`006`000.00 uah (not including WAT) | |
Agreement number | 1 | |
Date of signing | 14.04.2020 | |
Type of announcement | Announcement of the auction for the sale of small-scale privatization objects |
Information about Supplier
Name of legal entity | ТОВАРИСТВО З ОБМЕЖЕНОЮ ВІДПОВІДАЛЬНІСТЮ "АВТОТЕХ-УНІВЕРСАЛ" | |
USREOU code | 38676889 | |
Legal address | 49000, Україна, Дніпропетровська область, м. Дніпро, площа Героїв Майдану, буд. 1, офіс 328 |
Documents of contract / changes
Signed agreement
|
ДКП_Локомотив.pdf | |
Signed agreement
|
ДКП_Локомотив.pdf | |
Decree on confirmation of privatization
|
Наказ_ЗВП_Локомотив.pdf | |
Decree on confirmation of privatization
|
Наказ_зняття_з_контролю_договорів_купівлі_продажу.pdf |
Nomenclature of the contract
1) |
Обє'кт незавершеного будівництва - водно-спортивна база "Локомотив". Загальна площа - 8101,6 кв.м. Число поверхів: 1 блок 3 поверхи, 2 блок 8 поверхів.
CAV-PS code: 04222000-0 - Магазин (гастроном, універмаг, мінімаркет), аптека, перукарня, хімчистка, пральня, лікарняно-оздоровчий заклад, фізкультурно-оздоровчий заклад тощо
Legacy classificator code 018:2000: 242 - Інші інженерні споруди, не класифіковані раніше
The object is registering
|
8101.6 метри квадратні |
PERIODS
The status of the fulfillment of the stipulated conditions at a specific time point | Partly completed | |
Period type | Waiting for payment | |
Date when the deadline for action within Maystone runs out | 15.06.2020 18:00 | |
Date when the relevant conditions were fulfilled | 28.07.2021 10:20 | |
Date of period editing | 09.08.2021 10:25 |
The status of the fulfillment of the stipulated conditions at a specific time point | Completed | |
Period type | Completion of privatization | |
Date when the deadline for action within Maystone runs out | 17.08.2021 18:00 | |
Date when the relevant conditions were fulfilled | 06.08.2021 10:25 | |
Date of period editing | 09.08.2021 10:28 |
The status of the fulfillment of the stipulated conditions at a specific time point | Completed | |
Period type | Fulfillment of terms of sale | |
Date when the deadline for action within Maystone runs out | 06.08.2024 10:25 | |
Date when the relevant conditions were fulfilled | 10.11.2021 00:00 | |
Date of period editing | 02.12.2021 14:11 |
Contract in CDB
ID | ddd8ae91adb54ac39ffc4b7f9299c7b1 | |
ContractID | UA-PS-2020-03-08-000002-3-11 |