Будівля їдальні загальною площею 238,9 кв. м

Published
28.02.19
Payment is expected
till 02.05.19
The agreement is paid. The decree is expected
till 21.03.19
Period of fulfillment of the terms of sale (period of appeal)
till 11.03.22
The object privatization is completed.
The object privatization is completed.

Contract details

Contract amount 34`346.06 uah (not including WAT)  
Agreement number no data  
Date of signing 27.02.2019  
Type of announcement Announcement of the auction for the sale of small-scale privatization objects by method of step-by-step of lowering the starting price  

Information about Supplier

Name of legal entity СЕЛЯНСЬКЕ (ФЕРМЕРСЬКЕ) ГОСПОДАРСТВО "СЛАВУТИЧ"  
USREOU code 32150431  
Legal address 26522, Україна, Кіровоградська область, с.Перегонівка, вул. Аграрна 3  

Documents of contract / changes

Signed agreement
Договір 439.pdf  
Decree on confirmation of privatization
Наказ 174.pdf  
Decree on confirmation of privatization
Наказ 12_05_47_ДКП.pdf  

Nomenclature of the contract

1)
Відомості про об’єкт: окремо розташована одноповерхова будівля площею 238,9 кв.м; фундаменти бутові, стіни цегляні, покрівля шиферна, перекриття - дерев’яні балки, залізобетонні плити; підлога із мозаїчного бетону. Рік побудови – 1992. Технічний стан аварійний. Балансова вартість відсутня. Відомості про земельну ділянку: земельна ділянка окремо не виділена.
CAV-PS code: 04223000-7 - Заклад харчування (кафе, бар, ресторан тощо)
Legacy classificator code 018:2000: 125 - Будівлі промислові та склади
The object is registering
238.9 метри квадратні

PERIODS

The status of the fulfillment of the stipulated conditions at a specific time point Completed  
Period type Waiting for payment  
Date when the deadline for action within Maystone runs out 02.05.2019 19:00  
Date when the relevant conditions were fulfilled 01.03.2019 09:05  
Date of period editing 06.03.2019 09:06  
The status of the fulfillment of the stipulated conditions at a specific time point Completed  
Period type Completion of privatization  
Date when the deadline for action within Maystone runs out 21.03.2019 18:00  
Date when the relevant conditions were fulfilled 11.03.2019 15:15  
Date of period editing 11.03.2019 15:24  
The status of the fulfillment of the stipulated conditions at a specific time point Completed  
Period type Fulfillment of terms of sale  
Date when the deadline for action within Maystone runs out 11.03.2022 15:15  
Date when the relevant conditions were fulfilled 26.06.2020 15:00  
Date of period editing 26.10.2020 16:53  

Contract in CDB

ID a64b920e2c4f487cab4a5d69af46eb7b  
ContractID UA-PS-2018-12-30-000020-2-11